Mykolaiv Capital Construction Department spent ₴43 million in October, but is still the worst performer in terms of budget implementation

УКБ Миколаєва за десять місяців виконало лише 30% плану видатків — найменше серед підрозділів мерії. Фото: міськрадаOver ten months, Mykolaiv’s Capital Construction Department has implemented just 30 per cent of its expenditure plan — the lowest among the city council’s departments. Photo: City Council

The Mykolaiv Capital Construction Department (CCD) has spent only 25 per cent of its annual budget in the first ten months of 2026. This is the lowest figure among the city council’s departments. Overall, expenditure over the ten-month period stands at 85.5 per cent of the plan for this period, which amounts to 72.7 per cent of the annual budget.

This is evidenced by official data on the utilisation of Mykolaiv’s budget as at 1 November, which was analysed by NikVesti.

In total, between January and October, 5.98 billion hryvnias were spent from Mykolaiv’s budget out of the 6.99 billion allocated for this period. Consequently, over one billion hryvnias of the ten-month budget remained unspent.

Meanwhile, the city’s annual expenditure plan, taking into account amendments, stands at 8.22 billion hryvnias. This means that by early November, approximately 72.7 per cent of the funds allocated for the whole of 2026 had actually been spent.

The Capital Construction Department has spent only 29 per cent of the planned funds

The Capital Construction Department of the Mykolaiv City Council has the lowest budget implementation rate. Over ten months, the department spent 71.1 million hryvnias out of the 241.6 million planned for this period. This amounts to just 29.4 per cent. Consequently, 170.5 million hryvnias of the planned budget remained unspent.

At the same time, the department’s expenditure increased significantly compared with the previous month. Over the first nine months, the Capital Construction Department spent just 28.1 million hryvnias, or 13.4 per cent of the budget. Thus, in October, the department spent a further 43 million hryvnias – more than in the previous nine months combined.

However, the greatest shortfall to date is still observed in the funding of construction works.

Of the 220 million hryvnias earmarked for capital expenditure over ten months, the department has spent 56.6 million hryvnias, or 25.7 per cent.

By contrast, funds for staff salaries and related contributions were used almost in full — 13.1 million hryvnias out of the 13.6 million planned, or 96.4 per cent.

Who else is falling behind schedule

Apart from the Capital Construction Department, five other city council departments have implemented less than 80 per cent of their expenditure plans.

In particular, the Inhulskyi District Administration spent 43 million hryvnias out of the 61.4 million planned. This represents 70.1 per cent of the plan.

The Korabelnyi District Administration spent 44.4 million hryvnias out of 61.2 million, or 72.5 per cent.

The Health Department spent 133.8 million hryvnias out of the 182.6 million planned. This represents 73.3 per cent of the budget.

The administrations of the Central and Zavodskyi districts have slightly higher figures. The former achieved 79.2 per cent of its budget, spending 55.9 million hryvnias, whilst the latter achieved 79.7 per cent, spending 52.4 million hryvnias.

By way of comparison, the Education Department, which has the highest expenditure among the city council’s departments, spent 2.32 billion hryvnias, or 87.6 per cent of its budget. The Department of Municipal Services spent around 1.21 billion hryvnias, fulfilling approximately 86 per cent of its budget.

However, a low percentage of implementation does not necessarily mean that no work was carried out. The report reflects only the budget payments actually made, rather than the volume of work completed by contractors.

Why the City Construction Department is failing to spend budget funds

As a reminder, NikVesti previously investigated why Mykolaiv is failing to spend its allocated funds and how payment delays by the Treasury are affecting construction and renovation work in the city.

At the time, Oleksii Savchuk, Head of the Capital Construction Department, stated that due to restrictions imposed by the Treasury, the city was unable to pay contractors for part of the work already completed.

According to him, as of October, the Treasury held 22 certificates of completion totalling nearly 29 million hryvnias.

«Since 14 September, when the Treasury stopped making payments, we have accumulated nearly 30 million hryvnias in unpaid invoices. This includes both the payments that were already with the Treasury at that time and those we submitted later,» said Oleksii Savchuk.

In addition to payment delays, the official attributed the low budget execution rate to the need to amend project documentation, undergo further expert reviews and carry out procurement procedures.

Before the payment issues arose, the department had expected to use around 70 per cent of the planned funds by the end of the year. However, following the introduction of restrictions, Oleksii Savchuk was unable to predict how much money would be spent by the end of 2026.

He also reported that the department is prioritising the completion of work on projects funded by state grants so as not to lose these funds.

Furthermore, budget implementation is affected by delays in the preparation and amendment of project documentation, the conduct of procurement procedures and the implementation of construction projects.

For his part, Mayor Oleksandr Sienkevych had previously attributed the CCD’s poor performance to a lack of funds. According to him, the city prioritises spending on salaries, utilities and other essential needs, whilst funding for capital works is often deferred until the end of the year.

Meanwhile, Mykolaiv continues to face a shortage of funds for its most pressing needs. As previously reported by NikVesti, in October the city council appealed to the state for the third time, requesting an additional 819.1 million hryvnias by the end of the year. The city was most short of funds for water supply, heating, salaries and utilities.