A working group has been set up in Mykolaiv to modernise the nursery, which has been undergoing renovation since 2018

Дитячий садок №87 в Ракетному Урочищі, жовтень 2020 року, архівне фото МикВістіNursery School No. 87 in Raketne Urochyshche, October 2020, archive photo NikVesti

In Mykolaiv, there are plans to modernise Nursery School №87 «Vyshenka» in Raketne Urochyshche, where renovation work has been ongoing since 2018. Previously, the city authorities had promised to complete the work and reopen the nursery in 2025. The nursery has now been included in a new energy-efficiency modernisation project funded by international grants.

The relevant order was signed on 9 November by the mayor, Oleksandr Sienkevych, according to NikVesti.

The document provides for the creation of two working groups, which will be responsible for modernising the nursery and the energy infrastructure of the city’s electric transport system. Both areas will be funded as part of a single grant project, for which Mykolaiv has secured over 3 million euros.

In particular, work is planned at Nursery School №87 to improve the building’s energy efficiency. This should help reduce the energy costs associated with heating and electricity supply for the facility.

The Capital Construction Department of Mykolaiv City Council will be responsible for this aspect of the project. The working group is headed by Deputy Mayor Serhii Korenev. Its members also include First Deputy Mayor Vitalii Lukov, Head of the Education Department Hanna Lychko, and representatives of the Capital Construction Department.

The other part of the project concerns the city’s electric transport system. It involves the modernisation of the energy infrastructure, for which the municipal enterprise «Mykolaivelektrotrans» will be responsible. The working group is headed by Deputy Mayor Yurii Andriienko.

The working groups established are tasked with organising procurement, monitoring the execution of works, approving project documentation and ensuring compliance with the requirements of the international grant provider.

The project is being implemented with funding from Denmark via the Nordic Environment Finance Corporation (NEFCO). However, the new order does not specify when exactly the work will begin or when the nursery will be able to admit children.

The nursery has been undergoing renovation for eight years now

As a reminder, major renovation work on Nursery School №87 «Vyshenka» in Raketne Urochyshche began back in 2018. The work has been repeatedly delayed due to funding issues, and following the outbreak of full-scale war, the building also sustained damage.

In December 2024, the mayor, Oleksandr Sienkevych, promised to open the nursery in 2025. He explained that the facility had originally been scheduled for completion in 2022, but the project had to be revised due to Russian shelling and damage to the building.

«I plan to complete this project in 2025 and welcome the children there — it will be fully operational. I am personally overseeing this matter,» Oleksandr Sienkevych said at the time.

In February 2025, Alla Lutska, Director of the Department of Energy, reported that the building was 85 per cent ready prior to the full-scale war. According to Prozorro, 13.8 million hryvnias had already been allocated for the refurbishment, excluding the costs of project documentation.

To complete the work, a further 15.8 million hryvnias has been earmarked in the city’s 2025 budget. These funds were intended, in particular, to landscape the grounds, install underfloor heating in the swimming pool area and commission the fire-alarm system.