View full version

More than ₴313 million is needed to restore the facilities of «Khersonoblenergo» due to Russian shelling

Зруйнована електропідстанція «Нікольська». Фото: «Херсонобленерго»Destroyed power substation «Nikolska». Photo: «Khersonoblenergo»

The key substations and overhead lines of JSC «Khersonoblenergo» have been heavily damaged by Russian shelling. At least 313.5 million hryvnias is needed to restore the damaged power facilities.

This was reported by the company's press service in an appeal to international partners.

Key substations in the region suffered the most critical damage: «Posad-Pokrovska», «Tryfonivska» and «Oleksandrivska». Prior to the Russian strikes, they supplied electricity to 77 settlements with over 35,500 consumers. Currently, at least 293 million hryvnias is needed to restore these substations.

Підстанція «Олександрівська». Фото: «Херсонобленерго»Substation «Oleksandrivska». Photo: «Khersonoblenergo»
Підстанція «Бериславська». Фото: «Херсонобленерго»Substation «Beryslavska». Photo: «Khersonoblenergo»

In addition, another 25.3 million hryvnias are needed to restore power lines destroyed during the attacks.

Зруйновані електромережі. Фото: «Херсонобленерго»Destroyed power lines. Photo: «Khersonoblenergo»
Зруйновані електромережі. Фото: «Херсонобленерго»Destroyed power grids. Photo: «Khersonoblenergo»

Earlier, the Kherson City Military Administration reported when the CHPP, which was suspended due to Russian shelling, could resume operations.

View full version