Part of a village in the Mykolaiv region was without water for almost a month due to the replacement of the water tower
- Julia Lukyanenko
-
•
-
14:36, 16 November, 2026
due to a rusty water tower. Illustrative photo: UNOPSIn October, major repairs to the water supply system began in the villages of Bilozirka and Novomykolaivka in the Mykolaiv region. Old, rusty water towers, which were no longer functioning properly, are being replaced. Whilst a temporary water supply system was set up in Novomykolaivka, part of Bilozirka has been without water since mid-October.
NikVesti investigated why this situation arose in the village and what solution was found for the residents.
Replacement of rusty water towers
The villages of Bilozirka and Novomykolaivka are located in the Zavodske community. The United Nations Office for Project Services (UNOPS) is managing the project to carry out major repairs to the water supply systems.
On 7 October, UNOPS reported that the water pressure was low and there was a significant amount of rust due to corrosion of the water tower tanks. There were frequent interruptions to the water supply. In addition, some water was lost during pumping due to outdated fittings. The repairs are scheduled to take two months.
Part of Bilozirka without water
Residents of Bilozirka told NikVesti that on 14 October, the local council had warned of a water cut due to the replacement of the tower in the 3rd district. The estimated duration given was two months. People were asked to stock up on as much water as possible.
However, almost a month later, half the village was still without water. Nataliia Ovchinnikova, head of the «Suziria» housing and communal services company in Bilozirka, confirmed to NikVesti that water was available in one half of the village. According to her, the water main in the third district of Bilozirka had been replaced even before the war, so the problem lay with the old water tower.
«In the third district, the tower had rotted, and brown water was coming out. We’d been asking for a long time (to replace the tower, — note). The community found an organisation, and they started work. We thought it would be quick, but according to the documentation, the project is due to be completed by the end of the fourth quarter,» said Nataliia Ovchinnikova.
As for where residents should get their water from, the head of the «Suzirya» Housing and Communal Services Company replied that they could do so in the other part of the village.
«You can get water on the other side of the village. Every household has a water tank,» explained Nataliia Ovchinnikova.
She added that water was usually delivered by a fire engine, but this is currently not possible.
«When the fire engine arrives, it is loaded with fire-extinguishing powder. That’s why it can’t come,» noted the head of the «Suziria» Housing and Communal Services Company.
According to her, the Zavodske community is delivering drinking water; in particular, they were providing 12 litres per person.
What UNOPS has to say
Mykhailo Turianytsia, a communications specialist at UNOPs in Ukraine, explained that the bulk of the work involves replacing the water towers. In both Bilozirka and Novomykolaivka, the project involves dismantling the old towers and their foundations, constructing new foundations, waterproofing them, and erecting new towers.
«After that, work will continue on the installation of automated drainage wells, the fitting out of associated infrastructure and the connection of networks,» said Mykhailo Turianytsia.
He noted that work had begun earlier in Novomykolaivka. A new foundation for the towers has already been laid there, and waterproofing is currently underway. A temporary water supply system is in operation in the village.
In Bilozirka, the old tower was dismantled along with its foundation, and work has begun on constructing a new one. However, no temporary water supply system had been planned for the village. Mykhailo Turyanytsia noted that this decision had been agreed with the local authorities.
UNOPS confirmed that they received complaints last week regarding the lack of water.
«We spoke to residents and held consultations with the contractor — water should now be supplied on an hourly schedule. «We understand that this is an inconvenient situation and are doing our utmost to complete the work as quickly as possible and restore a permanent water supply,» said Mykhailo Turyanytsia.
The hourly schedule will remain in place for several weeks. Full water supply, as noted by UNOPS, is due to be restored once the new water tower has been installed and the pipelines, equipment and automation systems have been connected.
In both villages, all work is scheduled to be completed in December.
NikVesti previously reported that members of the Mykolaiv Regional Council had recommended that the Yelanets community set aside around 1.5 million hryvnias for the preparation of design and cost estimate documentation for the internal water supply networks. At the time, it was noted that the state was prepared to fund the construction of the main section of the water supply system to the tune of over 237 million hryvnias; however, the community would need to provide the networks through which water would be supplied directly to the settlement.
Subsequently, members of the Yelanets Settlement Council did not support the consideration of the issue regarding the preparation of design and cost estimate documentation for the construction of centralised water supply networks in Yelanets.