The Mykolaiv Capital Construction Department wishes to extend the construction site near the Arkas Lyceum until 2028, but they promise to complete the work next

Відновлений фасад ліцею імені Миколи Аркаса у Миколаєві. Фото: «МикВісті»The restored façade of the Mykola Arkas Lyceum in Mykolaiv. Photo: NikVesti

The Capital Construction Department of Mykolaiv City Council plans to extend the right to use the plot of land on which the reconstruction of the Mykola Arkas Gymnasium is underway until 2028. At the same time, they still promise to complete the restoration of the school by the end of 2027.

The relevant draft resolution was considered during a meeting of the parliamentary committee on ecology and natural resource use on 24 November, according to NikVesti.

The plot in question covers an area of over 5,700 square metres at 34 Nikolska Street, where work is currently underway to restore the gymnasium.

Oleksii Savchuk, head of the City Council’s Capital Construction Department, explained in a comment to NikVesti that the right to use the land is necessary for the department, as the client for the construction project, to obtain the necessary permits.

«The completion of the Arkas Lyceum project is scheduled for the end of 2027. This is a procedural matter concerning the plot of land, as we are acting as the project clients there. And in accordance with the Law of Ukraine «On the Regulation of Urban Development», in order to obtain a permit, we must secure either ownership or a right of use,» explained Oleksii Savchuk.

He noted that even if the contractor completes the construction work by the end of 2027, the school may not be commissioned until 2028. By that time, the department must also hold a valid right of use for the plot of land.

«Well, for example, they’ll finish the work in December 2027, and then in January 2028 we’ll be commissioning it there. And we won’t be able to do so because, by the time of commissioning, the land plot will have been revoked — that is, the right of use,» explained the official.

However, the members of the land commission were unable to vote on extending the right to use the plot of land due to the lack of a quorum.

Read also the NikVesti article «Reconstruction of the Arkas Lyceum in Mykolaiv is scheduled for completion in 2027».

The Arkas Lyceum during the war

The historic building of the Mykola Arkas Lyceum was destroyed on 1 November 2022 during the bombing of Mykolaiv by Russian forces. As a result of the shelling, part of a wall at the gymnasium collapsed, exposing the interior of the school classrooms, and the roof above the facade was damaged.

Ukrainian architects presented options for the reconstruction and restoration of the Lyceum to the Danish Ambassador, Ole Egberg Mikkelsen. For his part, he assured them that the city authorities would choose the reconstruction option themselves. Mayor Oleksandr Sienkevych subsequently announced that the school would be rebuilt whilst preserving its authentic appearance.

Work on rebuilding the lyceum began as early as the winter of 2025. Its reconstruction is being funded by the Danish government, whilst the United Nations Office for Project Services (UNOPS) is overseeing the work.