The building on Pohranychna Street in Mykolaiv, damaged as a result of Russian shelling, may be left with two entrances

Стан багатоповерхівки після демонтажу третього та четвертого підʼїздів. Фото: МикВістіThe condition of the block of flats following the demolition of the third and fourth entrances. Photo: NikVesti

Mykolaiv City Council is considering two options for the future of the building at 43 Pohranychna Street, which was damaged by Russian shelling. It may be left in its current two-entrance configuration, or funding may be sought to rebuild the dismantled third and fourth entrances. A final decision has not yet been made.

This is discussed in the NikVesti article «Cracks, mould and no plan: how people live in a half-demolished building in Mykolaiv».

It should be recalled that for a long time, the building’s residents refused to agree to the demolition and tried to delay it. They claimed that of the 36 flats deemed unfit for habitation, 23 remained intact. The residents also believed that the city authorities had no interest in restoring the building, and that its demolition might be used to obtain cheap building materials.

However, the residents eventually agreed to the work, fearing that the building might suffer further damage due to the weather conditions.

Tetiana Honcharova, a resident of one of the flats in the demolished section of the building, explains that over the course of a year, representatives from the Department of Municipal Services met with residents on numerous occasions and insisted on the demolition. They explained that construction firms were only willing to consider rebuilding the building once the rubble had been cleared away, rather than working amongst the ruined structures.

«So, after demolition, the restoration should have taken place more quickly. In the end, I agreed. But over the course of a year, neither sponsors nor a programme that our block could join were found. Although the first deputy director of the Department of Municipal Services (Housing and Communal Services), Ihor Nabatov, told me that there were programmes under which our block had been considered for restoration. But nothing came of it. Why? Because there’s a co-operative block nearby, and we found ourselves, as it were, in a worse position. Back then, the residents didn’t organise themselves or set up a homeowners’ association, so our block wasn’t considered for any of the programmes,» says Tetiana Honcharova.

Мешканка однієї з демонтованих квартир Тетяна Гончарова. Фото: МикВістіTetyana Goncharova, a resident of one of the demolished flats. Photo: NikVesti

In 2026, the Department of Urban Services carried out a commission inspection of the building and also commissioned a technical survey of its structures from the private company «A-Architect». Based on the results of the survey, a technical report was drawn up on 28 August 2026, in which the building’s overall damage category was classified as II (41–80 per cent).

According to the report, flats №1–34 are in a satisfactory technical condition, whilst flat №35 is in a state of disrepair. Flats №36–70 were located in the demolished part of the building. Consequently, 35 flats remain in the surviving part.

In response to an information request from NikVesti, the Department of Municipal Services stated that the city council and its executive bodies are continuing to seek opportunities to secure funding for the building’s restoration. At the same time, no final decision has yet been made regarding the future use of the demolished part of the building.

In particular, the building was considered for inclusion in the «Housing Renovation for Empowerment and Opportunities» (HOPE) project. During the stage of compiling the list of properties for funding, it was considered together with the neighbouring building №43A as a single cluster.

However, building №43A did not meet the project’s criteria, as the land on which it stands is under permanent use by the owners’ association. The final selection of buildings for the project is carried out by the project management. Consequently, neither building was included in the list of properties selected for funding.

The city council noted that experts are currently considering two possible options for the building’s future use: to restore the third and fourth entrances, or to leave it in its current configuration — as a building with two entrances, without restoring the dismantled section.

«Selecting the final option requires a comprehensive assessment of technical feasibility, the scope of the necessary construction works, their estimated cost and the possibility of securing the relevant financial resources,» the document states.

However, as of the date this response was prepared, the city council had not determined either the final option for the future use of the demolished part of the building, nor the sources of funding, the estimated cost, or the timeframe for any potential restoration work. The response also did not specify which other donors or organisations the city had approached for funding.

The history of the building at 43 Pohranychna Street

As a reminder, in October 2022, the Russians targeted a high-rise block at 43 Pohranychna Street. Seven people were killed, including a 12-year-old boy.

In April 2024, a decision was taken to demolish the building.

The flat owners at 43 Pohranychna Street refused to have their ruined homes demolished. At the time, the Mykolaiv Department of Housing and Communal Services stated that they did not know how to resolve the issue of the residents’ refusal. Mayor Oleksandr Sienkevych explained that the locals’ fears stemmed from concerns that the plots of land might be used for the construction of luxury properties.

Prior to this, the Mykolaiv Department of Housing and Communal Services had stated that residents of the semi-ruined buildings at 54 Krylova Street and 43 Pohranychna Street might lose any chance of future restoration if they refused to consent to the demolition. Later, however, they were told that they would still be able to receive housing certificates.

In November 2023, the Department of Housing and Communal Services stated that the destroyed high-rise block at 43 Pohranychna Street could be rebuilt, although this would only be confirmed following the demolition work and a further inspection of the building’s foundations.

Part of the building was demolished in 2024.

Later, the Central District Court handed down a sentence to a 30-year-old man from Mykolaiv and his mother. They passed on information to the Russians, as a result of which the Russian Federation launched a missile strike on the high-rise block at 43 Pohranychna Street. Seven people were killed as a result, including a child.