The auditors found asbestos in the cost estimate for the renovation of a sports college in Mykolaiv, worth almost ₴70 million
  • Saturday

    21 November 2026

The auditors found asbestos in the cost estimate for the renovation of a sports college in Mykolaiv, worth almost ₴70 million

Alina Kvitko 
Один з відновлених корпусів Миколаївського фахового фізкультурного коледжу, 2024 рік. Фото: архів МикВістіOne of the renovated buildings at the Mykolaiv Vocational College of Physical Education, 2024. Photo: NikVesti archive

In the documents relating to the 67.9 million hryvnias renovation of the dormitory block at the Mykolaiv Vocational College of Physical Education, auditors discovered materials containing asbestos, the use of which is prohibited in Ukraine. The regional capital construction department explained that these materials had been included in the cost estimate due to the peculiarities of the computer programme, and assured that there was no evidence of the actual use of asbestos.

This is stated in the procurement monitoring report, which was launched on 4 November by the Western Office of the State Audit Service of Ukraine, according to NikVesti.

The project concerns the major refurbishment of the college’s four-storey accommodation block at 41 Pohranychna Street. The client for the works is the Department of Urban Planning, Architecture, Capital Construction and Development Project Support of the Mykolaiv Regional Military Administration.

AdvertisingHide ads

During the audit, the auditors discovered that the tender documentation and the already concluded contract for the renovation provided for the use of asbestos cardboard 4 and 6 millimetres thick, as well as asbestos cord with a diameter of 8–10 millimetres.

However, Part 3 of Article 28 of the Law of Ukraine «On the Public Health System» prohibits the use of asbestos and materials containing it during construction work on any premises.

Asbestos is a group of natural minerals whose fibres can enter the lungs when dust is inhaled. Exposure to asbestos is associated with a risk of developing serious diseases, in particular lung cancer and mesothelioma. In the past, asbestos-containing materials were widely used in construction due to their resistance to high temperatures.

Consequently, on 6 November, the auditors wrote to the department demanding an explanation as to why such materials had been included in the documentation and the contract, despite the legal ban.

In its reply dated 11 November, the department stated that there was no documentary evidence of asbestos being used during the renovation. Nor had any completion certificates, which would have included these materials, been signed.

The client explained the presence of asbestos in the cost estimate by citing the specific features of the AVK-5 software package, which is used to calculate construction costs.

«The mere fact that the relevant materials were included in the bill of quantities cannot be equated with the actual use of such materials during the construction and installation works; it is explained by the specific nature of the AVK-5 software package,» the department noted.

The department also gave assurances that measures would be taken during the renovation to prevent the use of asbestos and other prohibited materials. However, the response did not specify whether they plan to amend the cost estimate and remove these materials from it.

Advertising

Furthermore, the renovation project received a favourable expert opinion from the «Scientific and Technical Centre for Construction Expertise» LLC as early as 14 September 2026. The experts reviewed the documentation, in particular to ensure compliance with requirements regarding public health and epidemiological safety, as well as the cost estimate. Following the review, the project was approved.

According to the expert report, the total estimated cost of renovating the dormitory block is 129.8 million hryvnias. Of this amount, 98.5 million is earmarked for construction work, a further 3.4 million for equipment, furniture and fixtures, and 27.9 million for other expenses.

The documentation also states that, of the total estimated cost of the works and other expenses, 44 million hryvnias have already been accounted for as completed. This sum relates to the entire renovation project, not just the latest contract worth 67.9 million hryvnias.

Following the refurbishment, the four-storey building, with a total area of over 5,000 square metres, is expected to provide 200 beds. The project also includes the upgrading of the water supply, sewerage, ventilation, electrical networks, fire alarm and fire protection systems.

Apart from the issue of asbestos, the auditors asked the department to explain how the estimated cost of the refurbishment was determined and why the contract price did not specify the date on which the prices were calculated.

The regional military administration replied that the cost of the works had been determined on the basis of design and cost estimate documentation that had undergone expert review. The absence of a date in the contract was explained as a technical error that occurred whilst printing the document from the cost estimation programme.

NikVesti had previously reported on the tender announcement for the renovation of the dormitory block at the sports college in Mykolaiv, with an estimated cost of 69.3 million hryvnias. Following the procurement process, the contracting authority entered into a contract with Inter Stroi Group LLC for 67.9 million hryvnias. The work is scheduled to be completed by the end of 2027.