Mykolaiv CHP reports on almost 100% supply of heat to the townspeople

Mykolaiv CHP assured that heat is supplied to 99.9% of the citizens they serve.

Dmytro Myroshnichenko, director of CHP, told about this in a comment to NikVesti.

According to him, utility workers are currently repairing the networks along the Khersonske Shosse, but they should finish it by 19:00 today. No more emergency situations were recorded in the city.

«So far, heating has been applied to all users except for one house on Khersonske Shosse, 1b. It turns out 99.9%. One house, currently under construction. We plan to complete and provide heat by 19:00,» he said.

Earlier, Dmytro Myroshnichenko said that by December 1, all subscribers of the enterprise will be connected to heat.

As a reminder, the 2023-24 heating season in Mykolaiv began on November 14. As of the evening of November 18, the company Mykolaiv CHP connected half of the total number of consumers in Mykolaiv to heat. At the same time, in September, the CHP reported that it was 92% ready for the start of the heating season. The company only has to complete renovation work on two large areas.

As of the evening of November 20, there were dozens of apartment buildings in Mykolaiv without heating. In several districts of the city, repair works of heating networks are ongoing. Then the first deputy of Mykolaiv city mayor Vitalii Lukov announced that they plan to connect all residential buildings of Mykolaiv to heat in a few days. To do this, the employees of the CHP and regional thermal power plant are currently working on the elimination of surges.

On the evening of November 21 , there were still more than 400 apartment buildings in the city without heating.

The Mykolaiv thermal power plant said that delays in the supply of heat to multi-apartment buildings occurred due to large gusts on the main pipelines of the heating lines.

We will remind that the Mykolaiv Regional Military Administration stated that, despite the declarations of readiness for the heating season, Mykolaiv CHP did not fulfill its promises. In RMA, the enterprise is required to make personnel decisions.

After that, an official investigation was launched at the CHP to find the culprits. The chief engineer, who is responsible for the preparation and conduct of the heating season, was temporarily removed from his position. The head of the CHP noted that this does not mean that the chief engineer is to blame, everything will become clear after the completion of the official investigation, which will last about a month.